Idaho Supreme Court: Defendants Can Provide Evidence Of Building Defects

BOISE, Idaho – The Idaho Supreme Court on June 29 overturned a judgment awarding $152,998.04 to a construction company for a breach of contract, concluding that the trial court erred by barring the defendants from presenting testimony of alleged construction defects on the project (Perception Construction Management Inc. v. Stephen Bell, et al., No. 36955, Idaho Sup.; 2011 Ida. LEXIS 101).
Full story on lexis.com